Sunday, February 28, 2010

The foundation is nearing completion

16 volunteers assisted laying the foundation on 2/27 with block masons Ed and Ron Cescutti. It was a nice mix of First Baptist Church and Thankful Baptist Church. All in all a total of 113 work hours were expended! We didn't quite finish, but will pick up on later in the week and have the foundation finished by around noon on Tuesday.


We had twice the number of volunteers needed for this phase, but the turn-out was a pleasant surprise on a cold morning. The project has gained steam and we fervently hope we can start the floor system next Saturday.



Thanks to the volunteers: First Baptist: Frank Clements, Billy Cooper, Joel Fletcher, Bob Gibson, Bill Harrison, Jim Hunter, Bill Kerestes, Charles Mull, Ken Nance, Charles, Suscheck, Lynn Whatley, Richard York. Thankful Baptist: Bobby Couch, Darryl Ellis, William Jasper and Duane Reid.