We have just heard from the production superintendent at Wheelers, and he says they will not be able to complete the wall package for delivery for Saturday, April 10th, work.
The production schedule took a hit with since we have been on hold. We hope this does not inconvenience anyone.
The wall package will now be delivered on April 16th for raising on the 17th. And, to avoid a schedule extension after that, Bill Harrison is attempting to get the firemen to install the roof beginning on the 19th such that our April 2 4th date for windows,doors and other interior work will not change.
Check back here for updates.