Following last week's wait for materials, here is the projected schedule for the next few weeks.
Saturday, April 17 - raise the walls. Steve Hunt is the coordinator, and last word was that we have enough volunteers. Contact Steve if you have any questions (Happy birthday to those twins last Sunday. That's two years of miracle!).
Monday, April 19 - Porch . We have enough volunteers.
April 20 -23 - Rome firefighters will finish the roof. Thanks, guys!
Saturday, April 24 - calls for installing exterior doors, windows, perlins, attic bracing and deadwood. Rodney Robertson is the coordinator. He will need a total of 12 volunteers; check with Rodney to see how many he needs to fill out the crew.
Saturday. May 1 - Electrical work. Richard York has his crew ready.
Saturday, May 8 - Ceilings and wall insulation. Need crews of 6 and 8. Contact Carroll Peterson or John Head.